Sprint Planning Meeting 2021 01 21

Erik Moeller edited this page Jan 21, 2021 · 2 revisions

Sprint Check-In, SecureDrop, 2021-01-202

Sprint timeframe: Beginning of Day (PST) 2021-01-21 to Beginning of Day (PST) 2021-02-03

0) 1.7.0 check-in

Release issue: https://github.com/freedomofpress/securedrop/issues/5689 QA matrix: https://docs.google.com/spreadsheets/d/1RbFqgphiZZVuAFdvCwJQugTHQw8EWOQdCcPscCXMgQM/edit#gid=0

Two backport PRs pending:

One PR requiring backport:

Allie will proceed with RC4 after mtg, Mickael can assist

Kevin and Conor are focused on functional testing of RC3 currently.

1) Restating our priorities

  • Complete SecureDrop 1.7.0 QA and release

  • Complete key Focal deliverables

    • Attempt and document an initial Xenial->Focal migration on hardware
    • Land migration to unattended upgrades
    • Detect incompatible playbooks
    • Early investigation of 5.4 kernel
    • Fixing dual-distro support on apt-test
  • Prepare draft PR for "Safe Deletion" in Journalist Interface based on initial user research findings

2) Reviewing the timeline

2021-01-26: SecureDrop 1.7.0 Release
2021-01-28: PTO: Kushal
2021-01-29: PTO: Erik

After next sprint:

2021-02-09: SecureDrop 1.8.0 QA/Feature Freeze
2021-03-02: SecureDrop 1.8.0 Release (first release w/ Focal support)
2021-04-30: Ubuntu 16.04 LTS end-of-life
TBD       : SecureDrop 2.0.0 (Xenial, v2 support fully removed from codebase)

3) Reviewing tasks and team allocations

https://docs.google.com/spreadsheets/d/1idKk6ozSCwV4lZzJMYuY836pDU0EUQZS-Rp5vOEQgiY/edit#gid=0