Order your OpenBuilds Table Series
You will need:
- OpenBuilds Balldriver Set
- MDF/Ply/Sheet stock for top and optional shelf
TIP: Click on an image to see a larger view
Take the 4x 40x40 Leg extrusions, and attach a Caster Plate to the bottom of each as shown:

Measure 10.5in / +-270mm from the bottom, and make a mark on all 4 legs

Preassemble 8x Corner Brackets with M5x8mm Screws and Tee Nuts as shown, set aside for the next step:

Slide one each of these brackets down the leg, to sit above the Mark made in step 2.

Repeat for sliding another Corner bracket down the leg, on the adjoining edge as shown:

Carefully align the brackets with the mark, and tighten down securely

Repeat steps 4-6 above, for the remaining 3x legs.

Attach 4x Corner brackets to the first brace, using 12x Tee Nuts and M5x8mm Screws

Attach 4x Corner brackets to the second brace, using 12x Tee Nuts and M5x8mm Screws

Attach Frame extrusion to the Braces using 12x Tee Nuts and M5x8mm Screws. Ensure that the Brace is centered on the sides:

Slide in 3 Tee nuts into each end of the Side Frame extrusion as shown:

Loosely position the 4 legs as shown, on the ground, near one of the Frames assembled in the step before.

Raise the Frame assembly up and attach to the leg's corner brackets using M5x8mm screws into the Tee nuts from step 11, as shown

Take one more 20x60 Frame side extrusion and slide in 3x Tee nuts on each side

Attach this side piece to the Back as shown:

Repeat the steps above, to add 3x Tee nuts to each end of the 4th Frame extrusion

Attach the 4th Frame extrusion, to the Front as shown

Assembly 4x Corner brackets, with 3x Tee Nuts, and M5x8mm screws as shown

Attach these 4x corner brackets to the top of the legs as shown. Ensure you line them up flush with the top of each leg.

Assemble as shown using Tee Nuts and M5x8mm screws:

Attach them to the adjoing edge at the top of each leg, taking care to align them even with the top, just as you did for step 19:

Using 12x Tee Nuts as shown, attached another 2x Frame extrusions to the remaining Brace, ensuring that the Brace is centered on the sides:

Add 3x Tee Nuts to each end of the Frame as shown:

Position this frame assembly flush with the tops of the legs:

Attach to the Corner Brackets using M5x8mm Screws

Slide 3x Tee Nuts into each end of the Back Frame Extrusion

Attach the Back Frame Extrusion to the Corner Brackets using M5x8mm screws, taking care to align it flush with the top of the legs.

Slide 3x Tee Nuts into each end of the Front Frame Extrusion

Attach Front Back Frame Extrusion to the Corner Brackets using M5x8mm screws, taking care to align it flush with the top of the legs.

Slide 24x Tee Nuts into front and back frame pieces, on the front and back sides on both shelves as shown, 3x on each end:

Slide another 24x Tee Nuts into front and back frame pieces, on the left and right sides both shelves as shown, 3x on each end:

Attach 8x Corner Brackets using M5x8mm screws into the Tee Nuts from stel 30 and 31 above.

Align and L-Bracket flush with the top, and install using Drop-in Tee Nut, and M8x5mm Screw

Align the remaining L-Brackets flush with the top, and install using Drop-in Tee Nuts, and M8x5mm Screws. Position them where you plan on attaching the table top later:

Rotate the assembly onto its side, and attach the 4x Caster Wheels into the Caster Plates (Installed in Step 1)

Screw table top down to frame through the L-Brackets using cutting screws

Notch the corners 60mm as shown to allow shelf to fit

Your OpenBuilds Table System is now complete and ready for use!