Milestone 1 - SV UI Shared Component Library
Proposal: #444
Estimated Delivery: 3 weeks | Funding: 297,000 CC
Effort Rationale: 92 build hours plus 46 review-cycle hours plus 14 project management hours, estimated using Digital Asset's own day-level estimates for the Initiate Proposal page and the components that compose it, since that estimate already accounts for maintainer review. The milestone delivers the 8 remaining Look & Feel components in the governance-beta shared component library, sequenced first as they unblock the page-level work in Milestone 2, plus the Initiate Proposal page itself, which composes them.
Deliverables:
Shared UI component library - 8 components
The remaining Look & Feel components required by the SV governance UI, implemented against the established design system:
Initiate Proposal page
The governance page that composes the above components into a working end-to-end flow:
All deliverables are pull requests against canton-network/splice, each referencing its originating issue and this grant, following the repository's existing code style and CONTRIBUTING guide.
Acceptance Criteria:
- Each of the 9 in-scope issues is closed by a pull request merged into
canton-network/splice main, reviewed and accepted by the Splice maintainers.
- Each component matches the established SV UI design system and is covered by a basic render test.
- All 8 components are available for use by the page-level issues in Milestone 2.
- The Initiate Proposal page (#2623) renders and functions end to end using the components delivered in this milestone.
- CI checks pass on all accepted pull requests.
- A short milestone report is published listing the accepted PRs, validation performed, and any scope changes.
| Milestone |
Target Deadline |
Funding |
| Milestone 1: SV UI Shared Component Library |
End of Week 3 |
297,000 CC |
Dev Fund proposal: proposals/2026-06-FCS-splice-sv-ui-ux-improvements.md
Milestone 1 - SV UI Shared Component Library
Proposal: #444
Estimated Delivery: 3 weeks | Funding: 297,000 CC
Effort Rationale: 92 build hours plus 46 review-cycle hours plus 14 project management hours, estimated using Digital Asset's own day-level estimates for the Initiate Proposal page and the components that compose it, since that estimate already accounts for maintainer review. The milestone delivers the 8 remaining Look & Feel components in the
governance-betashared component library, sequenced first as they unblock the page-level work in Milestone 2, plus the Initiate Proposal page itself, which composes them.Deliverables:
Shared UI component library - 8 components
The remaining Look & Feel components required by the SV governance UI, implemented against the established design system:
Initiate Proposal page
The governance page that composes the above components into a working end-to-end flow:
All deliverables are pull requests against
canton-network/splice, each referencing its originating issue and this grant, following the repository's existing code style and CONTRIBUTING guide.Acceptance Criteria:
canton-network/splicemain, reviewed and accepted by the Splice maintainers.Dev Fund proposal:
proposals/2026-06-FCS-splice-sv-ui-ux-improvements.md