# Procurement Plan – 45 km Road + Bridge Project
### Employer: KeRRA
### Prepared by: Teresiah Muthee
| Item / Material | Quantity | Supplier | Delivery Date | Responsible Team |
|----------------------------|---------|---------|---------------|----------------|
| Crushed Stone (G3/G1) | 120,000 m³ | ABC Quarry | Month 2–10 | Procurement & Supply Chain |
| Gravel / Sub-base Material | 80,000 m³ | XYZ Quarry | Month 1–10 | Procurement |
| Asphalt Binder & Wearing Course | 45,000 tons | Asphalt Ltd | Month 12–24 | Procurement |
| Cement & Steel (Bridge) | 5,000 tons | Steel & Cement Ltd | Month 6–18 | Procurement |
| Fuel & Lubricants | 200,000 liters | Fuel Supplier | Continuous | Supply Chain |
| Road Furniture & Signage | Various | Local Suppliers | Month 18–24 | Procurement & Safety |